Road construction on Plainview Street and Honeycutt Road continues with the installation of sidewalks, concrete curbs and gutters, and building of the subsurface for the future road. Paving is expected to take place Nov. 1, 8 and 9.

Pershing Street will be closed on the south side of Honeycutt for crews to conduct work in that area from Nov. 1-9. A detour will be in place to re-direct traffic to Maricopa Groves Parkway.

Excavation for the retaining walls on the South side of the Union Pacific Railway began this week, with crews working from south to north. Construction of the bridge also continues as abutments and pier cross-members are put in place to provide support for the structure.