The Maricopa City Council approved the extension of a 16-inch water main down State Route 238 west of Maricopa Tuesday evening at their regularly scheduled meeting.

In a three-way agreement, a 16-inch water main will be extended one mile from its present location at Smith-Enke Road and SR 347 by Global Water Resources then the City of Maricopa will extend the line another three miles west along SR 238 with the goal of servicing the new Apex Motor Club location. The cost of the line is estimated to be about $750,000 per mile, possibly more.

The city’s share of the extension is $1.5 million, and Apex will kick in $1 million.

The city eventually is expected to recoup its $1.5 million from Global Water as developers build in the area and pay to tap into the new water main.

Global will also pay for the upsizing of the water main along the city’s three-mile extension area from 12-inch to 16-inch pipe.

At the city council meeting, a citizen asked members of the council what the city will gain from spending $1.5 million for the extension.

City Manager Rick Horst said the Maricopa city limits already extend west of the city into the area where the water line will be constructed. He said other municipal utilities also are available in the area.

“We are currently looking at making this as an economic development investment,” Horst said. “This is a program to have 100 percent of this returned to us by the utility. It is an investment with a full return of it back to the city. What this does for us is open up thousands of acres for future development, both residential and commercial. More importantly, as a part of our strategic plan process, we are looking at a long-range industrial park with a possible rail spur inland port. It will support future jobs. We are making a performance investment with 100 percent return in exchange for tens if not hundreds of millions in private investments.”

Ron Fleming, CEO of Global, said Monday that extending the 16-inch trunk line one mile west will improve water pressures and services to residents and businesses already in the area. The line extension will connect in the Estrella Gin area, near the location of the new fire department. The city also has the Estrella Gin business park, that is a 50+ acre, city-owned parcel located just west of the intersection of Edison Road and Roosevelt Avenue.